To create a Microsoft Project baseline, open the approved schedule and select Project > Set Baseline > Set Baseline. Choose the unnumbered Baseline, select Entire Project, and then select OK.
All DoD Program Execution
Explore all articles
To create a Microsoft Project baseline, open the approved schedule and select Project > Set Baseline > Set Baseline. Choose the unnumbered Baseline, select Entire Project, and then select OK.
A retroactive baseline change adjusts budget, earned value, actual cost, or related records associated with a previously reported period. It is not automatically prohibited. However, it should remain exceptional, receive
Undistributed budget is budget for authorized work that has not yet been assigned to a control account, summary-level planning package, or lower-level Work Breakdown Structure (WBS) element. In an Earned
Management reserve in EVMS is budget that the contractor holds outside the Performance Measurement Baseline for management control of unexpected, in-scope work. It remains within the Contract Budget Base, but
A baseline change request is a formal document used to propose, evaluate and approve a change to an established project baseline. In an Earned Value Management System (EVMS), the request
A replan adjusts the plan for authorized work, usually by revising the future schedule, budget time-phasing, or work package structure through change control. A rebaseline establishes a new approved measurement
A schedule changes PMB dates, logic, or time-phased budget only when the program approves a corresponding baseline change. Routine status updates and forecast revisions may move current dates, change float,
Baseline traceability is the ability to reconstruct every approved change from a prior baseline condition to the current Performance Measurement Baseline (PMB). A reviewer should be able to identify what
A performance measurement baseline, or PMB, is the time-phased budget plan used to measure the execution of authorized project or contract scope. It integrates scope, schedule, resources, and budget so
The difference between a control account vs work package is primarily one of management level and purpose. A control account is a management control point where scope, schedule, budget, earned