The difference between hard vs soft constraints is how severely each one restricts a schedule’s response to network logic. In a forward-scheduled network, a soft constraint prevents an activity from
All DoD Program Execution
Explore all articles
The difference between hard vs soft constraints is how severely each one restricts a schedule’s response to network logic. In a forward-scheduled network, a soft constraint prevents an activity from
Schedule leads can damage schedule quality because they allow a successor to start before its predecessor reaches the event defined by the relationship. That overlap may look efficient. However, it
The DCMA leads check identifies predecessor relationships that contain negative lag. A lead allows a successor activity to start or finish before the relationship would otherwise permit. For example, an
The DCMA 14 point assessment is a set of schedule metrics used to examine the structure, status and execution performance of an Integrated Master Schedule (IMS). It checks areas such
To trace the Microsoft Project critical path, start at the project completion milestone and follow its driving predecessors backward through the schedule. Use the Critical Tasks format to see critical
Out of sequence progress occurs when an activity reports actual progress even though the predecessor condition defined in the schedule has not been satisfied. For example, a successor may start
Schedule lags are appropriate when a relationship requires a real, measurable passage of time and no work, resources, or meaningful progress occurs during that interval. A fixed curing, drying, cooling,
An effective IMS monthly status checklist does more than confirm that actual dates were entered. It verifies that the Integrated Master Schedule reflects current execution, produces a credible forecast and
A schedule recovery plan is a time-phased, resource-supported set of actions designed to restore an achievable contractual, program or internal milestone. It should identify the delay’s root cause, quantify its
Procurement schedule delays propagate through an Integrated Master Schedule (IMS) when a late purchase, approval, fabrication step or delivery pushes logically connected downstream work. The delay may first consume available