Negative float is the amount of time by which a schedule’s calculated completion date exceeds a required or targeted date. If an activity has negative 10 days of total float,
What Is a Driving Predecessor?
A driving predecessor is an immediate predecessor that currently determines the start or finish date of its successor through schedule logic. If the driving predecessor moves later, the successor will
DCMA High Float Check
The DCMA high float check identifies incomplete schedule activities with more than 44 working days of total float. Under the commonly used Defense Contract Management Agency (DCMA) 14-point schedule assessment,