Total float is the amount of working time an activity can be delayed without delaying the project finish date or another controlling schedule milestone. It measures schedule flexibility relative to
Free Float vs Total Float Explained
Free float measures how long an activity can slip without delaying an immediate successor. Total float measures how long it can slip without delaying the project finish or another controlling
What Is Negative Float and What Causes It?
Negative float is the amount of time by which a schedule’s calculated completion date exceeds a required or targeted date. If an activity has negative 10 days of total float,