Total float is the amount of working time an activity can be delayed without delaying the project finish date or another controlling schedule milestone. It measures schedule flexibility relative to
Total float is the amount of working time an activity can be delayed without delaying the project finish date or another controlling schedule milestone. It measures schedule flexibility relative to